42MW solar PV plant in New Zealand continues operations amid extreme flooding

Facebook
Twitter
LinkedIn
Reddit
Email
The solar PV plant (pictured) became New Zealand’s first grid-connected solar plant earlier this year. Image: Steven Woods (via Lodestone Energy/LinkedIn).

Despite severe flooding in the Waiotahe Valley in New Zealand, Lodestone Energy has confirmed that its 42MW Te Herenga o Te Rā solar PV power plant has continued operations.

Pictures released by Lodestone Energy on LinkedIn showed the solar PV power plant, which came online on New Zealand’s North Island in January 2025, mostly submerged in water.

This article requires Premium SubscriptionBasic (FREE) Subscription

Unlock unlimited access for 12 whole months of distinctive global analysis

Photovoltaics International is now included.

Not ready to commit yet?
  • Regular insight and analysis of the industry’s biggest developments
  • In-depth interviews with the industry’s leading figures
  • Unlimited digital access to the PV Tech Power journal catalogue
  • Unlimited digital access to the Photovoltaics International journal catalogue
  • Access to more than 1,000 technical papers
  • Discounts on Solar Media’s portfolio of events, in-person and virtual

Or continue reading this article for free

The solar PV power plant and the wider community in the valley were struck at the end of July and early August by a weather phenomenon called an “atmospheric river.”

An atmospheric river is a long, narrow band of concentrated water vapour in the atmosphere, resembling a river in how it transports moisture from one location to another.

These weather events often bring widespread rainfall, increasing the chances of flooding.

Lodestone Energy said the solar PV plant, which it claimed was the country’s first plant connected to the grid, had been designed to combat these extreme weather conditions.

Image: Lodestone Energy (via LinkedIn).

Indeed, despite being more costly than the average solar PV power plant, Lodestone Energy opted to raise the inverter stations and module connection boxes high above ground to ensure the plant could continue to operate in more than a meter of water.

The developer also adopted a special piling design that is more than 4 meters deep and has extra-high solar PV tables.

Through these measures, the 42MW Te Herenga o Te Rā solar PV power plant remained fully operational throughout the weather event. However, Lodestone Energy did note that its operations team decided, out of caution, to disconnect the plant from the grid when the rain had stopped and was assessing the plant.

Lodestone’s solar PV portfolio in New Zealand

Lodestone’s other operational solar PV power plants in New Zealand, the 33MW Kohirā in Kaitaia and the 32MW Rangitaiki plant, also situated near the Bay of Plenty, are connected to local distribution networks.

The company’s fourth solar PV plant, a 32MW development currently under construction in Whitianga, will connect to the Powerco distribution network.

The Rangitaiki PV plant incorporates agrivoltaics by featuring raised modules mounted on trackers, allowing sheep to graze beneath them. The modules in question are Trina Solar Vertex bifacial modules mounted on TrinaTracker’s Vanguard 2P tracker systems.

The Auckland-based company is also developing a 220MW agrivoltaics plant on New Zealand’s South Island.

Read Next

August 26, 2025
ABO Energy has closed its first syndicated loan agreement worth €240 million (US$279.8 million) to develop and construct more wind, solar and storage project.
August 26, 2025
Investment in utility-scale solar fell by 19% in the first half of 2025, as global investment in all renewable energy projects grew by 10%.
August 26, 2025
Jakson Engineers is investing over INR80 billion (US$912.5 million) to set up a 6GW integrated solar module, cell, and wafer plant.
August 26, 2025
India installed 14.3GW of new utility-scale solar capacity in the first half (H1) of 2025, marking a 49% increase year-on-year.
August 26, 2025
China has added 11.04GW of solar PV capacity in July 2025, a 48% decrease from the same period a year ago, according to data from China's National Energy Administration.
August 22, 2025
AEMO has predicted the NEM will see a steady rise in renewable energy generation capacity, reaching 229TWh by 2035.

Subscribe to Newsletter

Upcoming Events

Solar Media Events
September 16, 2025
Athens, Greece
Solar Media Events
September 30, 2025
Seattle, USA
Solar Media Events
October 1, 2025
London, UK
Solar Media Events
October 2, 2025
London,UK
Solar Media Events
October 7, 2025
Manila, Philippines