Australia’s NEM sees ‘record-breaking’ surge in renewables and energy storage assets

Facebook
Twitter
LinkedIn
Reddit
Email
613MW of solar PV reached full output in the third quarter of 2025. Image: AEMO.

The Australian Energy Market Operator (AEMO) has reported a record-breaking surge in new renewable energy generation and storage assets reaching full operation within the National Electricity Market (NEM).

The AEMO’s latest Connections Scorecard notes that, from 12 months to June 2025, 29 projects totalling 4.4GW have achieved full output.

This article requires Premium SubscriptionBasic (FREE) Subscription

Unlock unlimited access for 12 whole months of distinctive global analysis

Photovoltaics International is now included.

Not ready to commit yet?
  • Regular insight and analysis of the industry’s biggest developments
  • In-depth interviews with the industry’s leading figures
  • Unlimited digital access to the PV Tech Power journal catalogue
  • Unlimited digital access to the Photovoltaics International journal catalogue
  • Access to more than 1,000 technical papers
  • Discounts on Solar Media’s portfolio of events, in-person and virtual

Or continue reading this article for free

AEMO executive general manager system design Merryn York confirmed that the pipeline of new projects reaching full output in the NEM reached a record level in the 2024-25 financial year.

“The investment pipeline in the NEM continues to build, which is critical as decades-old generation approaches retirement. Pleasingly, 29 projects totalling 4.4GW of capacity reached full output this year, double last year’s total,” York said.

In the third quarter, spanning April to June, 10 projects reached full output. This includes 613MW of solar PV, two grid-forming battery energy storage systems (BESS) totalling 385MW, and a 100MW grid-following BESS.

These include the Wollar (280MW), Stubbo 2 (198MW), Wunghnu (75MW), Mannum 2 (30MW), and Kerang (30MW) solar PV power plants, as well as the Greenbank (200MW/400MWh), Koorangie (185MW/370MWh), and Latrobe Valley (100MW/200MWh) BESS sites.

Planning delays and complex grid connections

Despite the positives, integrating these assets into the NEM remains a complex and time-consuming process, which could damage future investment prospects in Australia.

According to the advocacy and engagement platform Clean Energy Investor Group’s (CEIG) latest 2025 Clean Energy Outlook, inconsistent planning requirements and delays were noted as major barriers to investment in renewables.

Additionally, projects being developed in Queensland could be stalled due to a new “strict” planning rule enshrined into law last week. This makes social licence requirements for solar PV power plants consistent with development assessment rules across Queensland.

At the end of June, 260 projects, totalling 53GW, were in the connections process within the NEM, marking a 39% increase in capacity compared to the same time last year. Of this, 7GW has already been built and commissioned for full output.

18 projects, totalling 6.5GW, have seen their applications approved in the third quarter. This includes 10 battery storage systems, totalling 2.4GW, one hydropower plant (2.4GW), four solar-plus-storage sites (1.7GW), two solar PV power plants (322MW), and one gas project (66MW).

AEMO confirmed that applications were approved in 9.4 months on average.

Our publisher, Solar Media, will host the Battery Asset Management Summit Australia 2025 on 26-27 August in Sydney. You can get 20% off your ticket using the code ESN20 at checkout.

Read Next

August 26, 2025
ABO Energy has closed its first syndicated loan agreement worth €240 million (US$279.8 million) to develop and construct more wind, solar and storage project.
August 26, 2025
Investment in utility-scale solar fell by 19% in the first half of 2025, as global investment in all renewable energy projects grew by 10%.
August 26, 2025
Jakson Engineers is investing over INR80 billion (US$912.5 million) to set up a 6GW integrated solar module, cell, and wafer plant.
August 26, 2025
India installed 14.3GW of new utility-scale solar capacity in the first half (H1) of 2025, marking a 49% increase year-on-year.
August 26, 2025
The Australian Government’s CER approved 56 new power stations, with 797MW of renewable energy capacity, in July this year.
August 26, 2025
China has added 11.04GW of solar PV capacity in July 2025, a 48% decrease from the same period a year ago, according to data from China's National Energy Administration.

Subscribe to Newsletter

Upcoming Events

Solar Media Events
September 16, 2025
Athens, Greece
Solar Media Events
September 30, 2025
Seattle, USA
Solar Media Events
October 1, 2025
London, UK
Solar Media Events
October 2, 2025
London,UK
Solar Media Events
October 7, 2025
Manila, Philippines